Phase 2 - Monday 13 February to Monday 29 May 2017

During Phase 2 Wirral line trains will start and terminate at James Street station from Monday to Friday. At weekends, all services will start and terminate at Birkenhead North and Birkenhead Central. Rail replacement buses will run between Birkenhead and Liverpool stations.

Travelling From Wirral - Monday to Friday

Travelling from Wirral - Monday to Friday

Wirral line services will terminate at James Street station between Monday and Friday. The Water Street entrance to James Street will be open from 05:37 to 22:00.

New Brighton & West Kirby

There will be timetable alterations and a 30 minute service will run on both the New Brighton and West Kirby lines throughout the work. Six car trains will run when possible to maintain the number of seats available.

13 - 17 February

We have carried out detailed safety assessments of our transport arrangements during all phases of the work. During the first week of Phase 2 (13 - 17 February) all Wirral line trains will start and terminate at one platform in James Street station. To ensure this platform does not become overcrowded we have had to make small changes to the timetable for the first 5 days of Phase 2, which will affect a small number of customers travelling into Liverpool via the New Brighton and West Kirby lines between 16:00 and 18:00. Passengers on these services will need to change trains at Hamilton Square station onto the next available Chester or Ellesmere Port service towards Liverpool.

20 February - 29 May

All New Brighton and West Kirby services will start and terminate at platform 1 in James Street station Monday to Friday. 

Chester & Ellesmere Port

If you travel from Ellesmere Port, Overpool or Little Sutton you will need to change at Hooton for services to James Street station between 07:12 and 18:12. Outside these hours, trains will run through to James Street platform 2.

Small timetable alterations will be made on both the Chester and Ellesmere Port lines throughout the work. 

Throughout Phase 2, Chester line services will start and terminate at James Street platform 2 Monday to Friday. 

Track Renewal Map Phase 2 Weedays New 950

Travelling around Liverpool City Centre

When you arrive in Liverpool, if you cannot complete your journey on foot from James Street station, valid rail tickets will be accepted on the 10A bus service, linking James Street, Moorfields and Lime Street stations. Rail tickets will be valid for journeys between Lime Street and Liverpool ONE as shown in the map.

10A Bus Route Combined

Travelling between North & South Wirral

If your journey normally involves changing between Wirral line services at Hamilton Square, you can continue to do so as trains will run through to James Street station between Monday and Friday.

Mersey Ferries

Cross-rail river tickets can continue to be used on all Mersey Ferry services until Sunday 19th February to help customers while only one platform is in use at James St station. After this date, you will still be able to use cross-river rail tickets on the Mersey Ferries at weekends, but not on weekdays.

Cyclists

As there are rail restrictions for cyclists throughout Phase 2 of the track renewal works, passengers travelling with a bike can continue to use valid cross-river rail tickets on any Mersey Ferry during all three phases.

Travelling From Liverpool - Monday to Friday

Travelling from Liverpool - Monday to Friday

All Wirral line trains will start at James Street station between Monday and Friday. Trains will not travel around the loop line, they will start at James Street and go straight to Wirral. A queueing system will be in place to help you move through the station as quickly as possible.

Ticket buying facilities will be limited at the main entrance to James Street station during peak times and special ticketing arrangements will apply. We advise you to purchase your
tickets at the Water Street entrance of James Street or any other station.

A revised timetable will be in place from James Street to Wirral and trains will depart at the times below.

James Street to New Brighton and West Kirby

James Street Departures First Train Minutes Past Hour Last Train
James Street to New Brighton 06:19 49 19 23:49
James Street to West Kirby 06:04 34 04 23:34


James Street to Chester* (Linking to Hooton for Ellesmere Port services)

James Street Departures First Train Minutes Past Hour Last Train
From 06:22 a 15 minute service will run 06:22 37 52 07 22  
From 19:07 a 30 minute service will run 19:07 37 07 23:37

* A service will also run between James Street & Chester at 05:52, Monday to Friday.


James Street to Ellesmere Port**

James Street Departures First Train Minutes Past Hour Last Train
Trains will run through to Ellesmere Port from 19:22 to end of service, Monday to Saturday 19:22 52 22 23:22

** A service will also run between James Street & Ellesmere Port at 06:07, Monday to Friday.

New Brighton & West Kirby

If you travel towards New Brighton or West Kirby, there will be timetable alterations and a 30 minute service will run on both the New Brighton and West Kirby lines throughout the work. Six car trains will run when possible to maintain the number of seats available. 

Chester & Ellesmere Port

If you travel to Ellesmere Port, Overpool or Little Sutton, you will need to change at Hooton between 06:56 and 19:26, Monday to Saturday. Outside these hours, trains will run through to Ellesmere Port.

Small timetable alterations will be made on both the Chester and Ellesmere Port lines throughout the work. 

Track Renewal Map Phase 2 Weedays New 950

Mersey Ferries

Cross-rail river tickets can continue to be used on all Mersey Ferry services until Sunday 19th February to help customers while only one platform is in use at James St station. After this date, you will still be able to use cross-river rail tickets on the Mersey Ferries at weekends, but not on weekdays.

Cyclists

As there are rail restrictions for cyclists throughout Phase 2 of the track renewal works, passengers travelling with a bike can continue to use valid cross-river rail tickets on any Mersey Ferry during all three phases.

Travelling from Wirral - Saturday & Sunday

Travelling from Wirral - Saturday & Sunday

There will be no cross-river trains at weekends, except for the Grand National Festival, Easter and May bank holidays.

New Brighton & West Kirby

If you travel from New Brighton or West Kirby, all trains will terminate at Birkenhead North.

There will be timetable alterations and a 30 minute service will run on both the New Brighton and West Kirby lines throughout the work. Six car trains will run when possible to maintain the number of seats available.

Chester & Ellesmere Port

If you travel from Chester or Ellesmere Port, all trains will terminate at Birkenhead Central.

If you travel from Ellesmere Port, Overpool or Little Sutton, you will need to change at Hooton for services to Birkenhead Central between 07:12 and 18:12, Monday to Saturday. Outside these hours, trains will run through to Birkenhead Central.

Small timetable alterations will be made on both the Chester and Ellesmere Port lines throughout the work. 

Rail Replacement Buses

High quality rail replacement buses will run directly between Birkenhead North and Liverpool and Birkenhead Central and Liverpool. Buses will stop at Moorfields and St George’s Hall on Lime Street.

Rail replacement buses will be scheduled to connect with train services at Birkenhead North and Birkenhead Central. Waiting time will be kept to a minimum and at peak times buses will fill up and go to keep you on the move.

If you use Birkenhead Park, Conway Park or Hamilton Square stations, Birkenhead rail replacement buses will run between Birkenhead North and Birkenhead Central as
shown in the map.

Travelling between North & South Wirral

If your journey normally involves changing between Wirral line services at Hamilton Square, Birkenhead rail replacement buses will link the stations as shown in the map below.

Track Renewal Map Phase 2 Weekend V3

Travelling From Liverpool - Saturday & Sunday

Travelling from Liverpool - Saturday & Sunday


Rail Replacement Buses

If you travel from Liverpool to Wirral, you will need to catch a rail replacement bus to either Birkenhead North, where trains to New Brighton and West Kirby will start or Birkenhead Central, where trains to Chester and Ellesmere Port will start.

High quality rail replacement buses will pick up at Moorfields and St George’s Hall on Lime Street, before travelling nonstop to either Birkenhead North or Birkenhead Central. Buses
to Birkenhead North and buses to Birkenhead Central will leave every 15 minutes at a minimum. At peak times buses will fill up and go to keep you on the move.

If you travel to Birkenhead Park, Conway Park or Hamilton Square, Birkenhead rail replacement buses will run between Birkenhead North and Birkenhead Central as shown in the map below.

New Brighton & West Kirby

If you travel towards New Brighton or West Kirby, there will be timetable alterations and a 30 minute service will run on both the New Brighton and West Kirby lines throughout the
work. Six car trains will run when possible to maintain the number of seats available.

Chester & Ellesmere Port

If you travel to Ellesmere Port, Overpool or Little Sutton, you will need to change at Hooton between 06:56 and 19:26, Monday to Saturday. Outside these hours, trains will run
through to Ellesmere Port.

Small timetable alterations will be made on both the Chester and Ellesmere Port lines throughout the work.

Track Renewal Map Phase 2 Weekend V3 New 950

Your Journey

Your journey time will increase by approximately 20 minutes, however at peak times when roads are busy journey time could increase further. To help everyone have the quickest journey possible, avoid travelling at peak times if you can and stick to public transport.

Assisted Travel

We will continue to provide dedicated support for customers with disabilities during Phase 2 of the work. Click here for detailed information. 

Bikes

Special arrangements are in place for passengers travelling with bikes in Phase 2. Click here for detailed information. 

 

Phase 3 Travel Information

Phase 3 Travel Information

Tuesday 30 May to Sunday 18 June 2017

Read more Phase 3 Travel Information

Assisted Travel

Assisted Travel

Travel information for passengers who require assisted travel

Read more Assisted Travel

Bikes

Bikes

Information for passengers wishing to travel with a bike during Wirral loop line track renewal.

Read more Bikes

Journey Planner

Journey Planner

Use our planner to quickly see how your specific journey will be affected during each phase of Wirral loop line track renewal.

Read more Journey Planner